OLGU ENERGY INVESTMENT GENERATION AND TRADE CO. INC. has been established in 2007 with the purpose to establish, commission, lease electrical energy production facilities, production of energy and sale of produced electrical energy.
200.25 MW Dinar Wind Power Plant in Dinar, Afyonkarahisar is among the main projects. The predicted annual production of plant is 564.000.000 kwh. and generation of CO2 over 285.000 ton will be prevented.
The provisional acceptance of the units has been completed and the relevant dates are as follows:
The provisional acceptance of the first seven units on December22, 2012, the provisional acceptance of the second seven units on February8, 2013, the provisional acceptance of the third seven units on March22, 2013, the provisional acceptance of 1 unit on July19, 2013, the provisional acceptance of the 12 units on November29, 2013, the provisional acceptance of the 16 units has been completed on August22, 2014, the provisional acceptance of the 17 units has been completed on December6, 2016, the provisional acceptance of the 4 units has been completed on December30, 2016, the provisional acceptance of the 5 units has been completed on January27, 2017 and the provisional acceptance of the last 5 units has been completed on February16, 2017.